Thursday, January 29, 2009








the shutters are going up for the up-stand beams and the lift core













we started the preperation for columns and the steel is going up





the tensioning cycle started






Thursday, January 22, 2009



ground floor slab ready for concrete, we will cast this weekend and we received inspection approval today

Wednesday, January 21, 2009





the work force on site




these are the photos of the ramp casted and completed. this was done on the 18th of Jan. we received the drawings.

Thursday, January 8, 2009




bottom steel for ground floor slab has been layed where the slab is completed, and all stairs are now ready for casting



we have waited to long for the approvals, a decision was made to erect the scaffolding for the groundfloor slab over the ramp steel and to cast the ramp afterwards, priority is to go up and this will only delay us if we had to wait