the shutters are going up for the up-stand beams and the lift core
we started the preperation for columns and the steel is going up
the tensioning cycle started
Thursday, January 22, 2009
ground floor slab ready for concrete, we will cast this weekend and we received inspection approval today
Wednesday, January 21, 2009
the work force on site
these are the photos of the ramp casted and completed. this was done on the 18th of Jan. we received the drawings.
Thursday, January 8, 2009
bottom steel for ground floor slab has been layed where the slab is completed, and all stairs are now ready for casting
wehavewaitedtolongfortheapprovals, a decisionwasmadetoerectthescaffoldingforthegroundfloorslabovertherampsteelandtocasttherampafterwards, priorityistogoupandthiswillonlydelayusifwehadtowait
All comments in this blog is that of my own and not from Gulf shore or Oryx if by any chance you find my wording offensive its done to give this blog some humor and is in no way pointed at anyone but the blog itself, i do hope you enjoy this as a new way of keeping you up to date on whats happening.
please smile and enjoy it for what its worth!