Tuesday, November 18, 2008

Question - Could you please inform when you expect to reach slabs # 5 and 8. What about building completion?
Answer - we are just waiting for this drawings without it i can't estimate these dates,but as soon as we receive it i will update you, I'm sticking with end 2009 for completion its my head thats out there to be chopped but i believe its possible so I'll take the risk.

Thursday, November 13, 2008

virtual tour 13-11-2008


just another quick update on the progress,

Wednesday, November 5, 2008

comments


please see previous video first, this then just a quick response from me.

virtual tour


This then the long awaited virtual tour, this will give you a more realistic view of what's happening and how the tower is created, i will update the virtual tour as much as possible as this will give you a better understanding of the works that is occurring, please be patient with me, this is my first video and more will follow, so will the the amount of people required to complete all these works, i hope you enjoy this and please let me know if this is a better way of posting or not. your feedback is important and I'm always happy to oblige.

ramp soffit





Sunday, November 2, 2008

stairs from promonant to ground

steel ready to be connected

we are now preparing the steel
stair soffit in the main core both sides prepared and ready for steel
stair soffit form the parking area

ramp

it will now be connected to the water tank soffit
the soffit for the ramp after it passed the water tank.

water tank

starting the formwork for the ramp soffit over the water tank
walls covered and watered to keep wet
all shutters removed

finish the casting