Sunday, May 25, 2008

Monday, May 12, 2008

Friday, May 9, 2008

the crane footing is casted as seen in picture 1 we will start erecting the crane Sunday 11May 08
Site at the current stage
The main lift steel are on the final binding
steel binding continue

when you take a look at the site photo you must remember that first we had to cast pcc the 2 layers of waterproofing membrane and then concrete screed to protect the membrane from getting damaged by the steel, but when we cast the prominent floor in mid to end May we will go much faster as this ground works do take more time than the rest