sorry everyone there seem to be a problem with this blog of mine now it gives me a code bX-cvu52 error so sorry no photos if anyone can tel me how to upload photos or give my an email account to send them to you so that we can upload them to skyscraper city. com for all to see, please help!
Okay we completed the dynamic test and got approval and now will be able to continue with the concrete, the crane footing and the rest of the pcc will be casted together, to speed up concrete works.
we have placed a screed over the waterproof membrane and started the steel binding inside the pile caps as well as the underground beams and the columns
we also completed the steel for the sub station footings,and are ready to join the prominent slab when we do the cast there
the drainage has been done and we are currently completing the sump pits
We lost a total of +- 49 days and will have to add this to our completion date, this was cause due to USA presedential visit, rain, sement shortages,ext. and will influence my completion date by the same